Project Procedure

We would like to show an real example of procedure for our export mold.

Mold layout: 1 Cav,ABS raw material,YUDO single open gate,LKM738H steel.


From order June 26th,2016 to mold shipment Sep 10th ,2016

Step.1 Order Confirmation

1-1(001).jpg

1-2(001).jpg


Step.2 Part Analysis

2(001).jpg


Step.3 DFMEA

3-1(002).jpg

3-2(002).jpg

3-3(002).jpg

3-4(002).jpg

3-5(002).jpg



Step.4 Mold Flow

4-1(001).jpg

4-2(001).jpg

4-3(001).jpg

4-5(001).jpg

4-6(001).jpg4-7(001).jpg
4-8(001).jpg4-9(001).jpg


Step.5 Mould 3D/2D Design

5-1(001).jpg5-2(001).jpg


Step.6 Cutting Tooling Steel Notice

Step.7 Inner Meeting /Start Order Steel/Moldbase

Step.8 Schedule report send to customer each Monday

8(001).jpg



Step.9 Moulding Trial Feedback (Parameter & Video & Dimensional Report etc)

9-1(001).jpg9-2(001).jpg9-3(001).jpg


Step.10 Further Improvement or Modification

Step.11 Final Checking before Shipment

11-1(001).jpg11-2(001).jpg11-3(001).jpg


Step.12 Packaging Information & Shipment

12-1(001).jpg12-2(001).jpg